Meeting with South East Water – Thursday 4 December at 7.00 pm Christ Church Horam

South East Water is working in Laundry Lane, Horam from Monday 5 January

We’re replacing around 630 metres of water main in Laundry Lane, Horam, to improve the water network in the area.
Work starts on Monday 5 January and is expected to take about 11 weeks.

Road closures:
Laundry Lane – from the junction with Horebeech Lane to the junction with Vines Cross Road
Vines Cross Road – we’ll also be closing a short section of Vines Cross Road from the junction with Laundry
Lane, from Saturday 14 February
Join us at Christ Church, Horam, between 4:00pm and 7:00pm on Thursday 4 December to find out more and
ask any questions.